Executive Summary
Mineral processing companies routinely make some of the toughest capital decisions in industry: designing facilities that process between 100,000 and 500,000 tonnes of ore per day while committing from a few hundred million to several billion dollars of capital. The decision taken during the early lock in performance for 20–30 years and determine whether a project delivers its promised returns or becomes a case study in stranded capacity and overruns.
Yet these decisions are still often made by "manual configuration exploration", meaning engineering teams test a handful of alternatives, refine one that looks reasonable, and move forward. There is usually no guarantee that this design is anywhere near the best that could exist, but we are used to work that way.
This article:
- Explains why plant configuration is a hard combinatorial problem even at the scale of a "toy" 150,000 tpd, $850M plant.
- Describes typical sources of uncertainty in mining projects: ore, equipment, system interactions, and market context.
- Introduces formal optimization methods that can find a provable optimum: a.k.a. "we hit the wall" in performance and value optimization. It is mathematically possible to prove this!
- Quantifies what this means financially: in realistic scenarios, these methods can protect or create $500M–$1B of value per major project with study costs in the $0.3M–$1.5M range.
The worked example uses mid‑scale numbers for clarity. For larger developments in the multi‑billion‑dollar range, the same percentage improvements translate into hundreds of millions to over a billion dollars in NPV impact. (... oh...did you say "political contraints"...we'll get to that also..be patient!)
Part 1: The Design Decision Challenge
The Billion-Dollar Dilemma
In the illustrative case we've created for this article, an owner sets a simple mandate for an expansion project:
- • Process 150,000 tpd. of ore
- • Stay within a $850M capital budget
- • Achieve at least 90% system availability.
On paper, this sounds straightforward. In reality, that single sentence hides thousands (literally thousands) of interdependent design choices:
- Mining source One pit or multiple pits, each with different ore characteristics and extraction costs.
- Primary crushing One large crusher vs. multiple smaller units.
- Grinding mill Conventional SAG + Ball vs. HPGR + Ball vs. alternative multi‑mill configurations.
- Flotation circuit Mechanical cells vs. columns vs. hybrid flowsheets.
- Thickening High‑rate vs. conventional thickeners.
- Water supply Fresh water, desalinated seawater, or recycled process water.
- Redundancy at each stage No redundancy, cold standby, or hot standby.
- Transport alternatives:... well, you got the idea!
Each decision has 2–6 alternatives, and the combination of five processing stages with three redundancy options each already creates thousands of possible configurations. In real projects, additional dimensions (tailings, power, multiple ore sources) multiply that space again.
And unlike choosing between coffee brands, picking the wrong grinding configuration does not just ruin your morning. It affects the next two or three decades.
The Real Stakes
These puzzles are not "theoretical" or mathematical curiosities (yes, I've heard that!..). The consequences are substantial:
| Consequence | Impact | Example Magnitude |
|---|---|---|
| Underestimated throughput | Plant cannot reach 150,000 tpd; downstream assets are stranded | $200M in wasted capital on oversized stages |
| Availability shortfalls | 10–20% below design production | $500M NPV loss over 10 years |
| Incompatible combinations | Wrong grinding–flotation pairing forces mid‑project rework | $50M–$100M retrofit costs |
| Budget overruns | Scope creep via "safety" redundancy and upgrades | $850M budget → $1.2B actual CAPEX |
| Missed synergies | Technologies fine alone but problematic in combination | $30M–$50M extra OPEX per year |
For larger copper projects with CAPEX in the $1B–$10B range, a 5–10% deviation in performance or cost can easily mean a $250M–$1B swing in value.
Executive teams cannot afford trial‑and‑error.(..although regularly they enjoy it!!). They need confidence that the chosen configuration is not just defensible, but mathematically unbeatable under the agreed assumptions.
Part 2: Sources of Uncertainty in Mining Projects
2.1 Ore Variability
Ore is not a controlled laboratory material. Even within a single deposit:
- Hardness fluctuates by 30–50% over time, changing grinding energy requirements and throughput.
- Metal grade varies, shifting revenue per tonne and influencing optimal cut‑offs and blends.
- Particle size distribution changes, altering crusher and mill behavior, flotation kinetics, and water balance.
- Impurities evolve (silica, clays, iron, etc.), affecting reagents and recovery.
A grinding mill sized for "nominal" ore hardness will either be under‑utilized (if ore is softer) or become a hard bottleneck (if ore is harder). Over‑designing to be "safe" adds capital cost; under‑designing erodes production.
2.2 Equipment Reliability and Failure Modes
Industrial equipment rarely achieves steady nameplate performance, because...well, they are real stuff so...
- Primary crushers: typical availability 90–94%.
- Grinding mills: 85–92%.
- Flotation cells: 88–95%.
- Pumps and conveyors: 90–97%.
- Water systems: 85–95%.
Failures tend to follow known patterns (patterns that can be modeled probabilistically), so exact failure timing even when unknown individually can be characterized and so is also possible to define interaction dependence on feed, operations, and maintenance. Design teams regularly feel they must decide: oversize, add redundancy, or accept lower availability; each option with different CAPEX and OPEX impacts.
2.3 System Interdependencies and Cascading Failures
A plant is a tightly coupled system, not a collection of independent machines:
- If crushing underfeeds grinding, mills starve.
- If grinding overfeeds or mis‑sizes particles, flotation suffers.
- If flotation underperforms, thickening sees variable loads.
- If water fails, everything stops.
A 5% availability loss in primary crushing can cascade into more than 10% production loss system‑wide:
- Crushing availability: 95%
- → Grinding sees 5% starved time → effective grinding capacity ↓5%
- → Flotation sees inconsistent feed → recovery from 88% down to 86%
- → Thickening throughput and water recycle suffer
- → Net effect: 10% production loss, not just 5%
This simple chain explains why "we'll just add some redundancy later if needed" is an expensive philosophy.
2.4 Market and Business Context Uncertainty
Designing for the next 20–30 years also means designing under:
- Commodity price volatility: Metal prices can swing ±30% year to year, turning a project NPV positive or negative.
- Environmental and social demands: Water rights, tailings regulations, and carbon costs change mid‑project and can restrict operating parameters or require expensive retrofits.
- Technology evolution: Innovations in extraction, automation, or energy supply may obsolete certain design choices or unlock new value.
- Labor and logistics availability: Remote sites struggle to attract skilled workforce; shipping costs fluctuate with fuel and geopolitics.
A "conservative" design approach (translate: "over redundancy" decision biases due to unstructured anxiety) protects against downside risk, but may sterilize upside opportunity. An "aggressive" design chases NPV, but risks chronic underperformance. Optimization helps manage this balance formally.
Part 3: The Decision Space: Size, Justification, and Difficulty
Why the Decision Space Is So Large
In the illustrative 150,000 tpd plant, the key technology choices are:
Stage 1 – Primary Crushing
- • Single large gyratory (simpler, cheaper)
- • Two parallel jaw crushers (modular, built‑in redundancy)
Stage 2 – Grinding
- • SAG + Ball (proven, standard)
- • HPGR + Ball (more efficient, higher control complexity)
- • Triple Ball Mill (flexible, high maintenance)
Stage 3 – Flotation
- • Mechanical cells (robust, higher water use)
- • Column flotation (efficient, chemistry‑sensitive)
- • Hybrid circuit (best potential, most complex)
Stage 4 – Thickening
- • High‑rate (compact, higher CAPEX)
- • Conventional (cheaper, larger footprint)
Stage 5 – Water Supply
- • Fresh water
- • Desalinated seawater
- • Recycled process water with supplement
Redundancy at each stage (independent decision):
- Option 0 No redundancy – 1‑out‑of‑1 failure → shutdown
- Option 1 Cold standby – 1‑out‑of‑2 one idle, activated on failure (+65% CAPEX)
- Option 2 Hot standby – 2‑out‑of‑3 two active, one spare (+120% CAPEX, higher availability)
Now, let's do the simple arithmetic:
| Stage | Technology Alternatives | × | Redundancy Options | = | Stage Configurations |
|---|---|---|---|---|---|
| Stage 1 (Crushing) | 2 (Gyratory, Dual Jaw) | × | 3 (None, Cold, Hot) | = | 6 |
| Stage 2 (Grinding) | 3 (SAG+Ball, HPGR+Ball, Triple) | × | 3 | = | 9 |
| Stage 3 (Flotation) | 3 (Mechanical, Column, Hybrid) | × | 3 | = | 9 |
| Stage 4 (Thickening) | 2 (High-rate, Conventional) | × | 3 | = | 6 |
| Stage 5 (Water) | 3 (Fresh, Desal, Recycled) | × | 3 | = | 9 |
| Total configuration space: | 26,244 | ||||
Total configuration space: 6 × 9 × 9 × 6 × 9 = 26,244 combinations.
If evaluating one configuration (flowsheet, simulation, CAPEX/OPEX estimate, availability analysis, environmental check) takes a modest 3 hours, then:
26,244 × 3 hours = 78,732 hours
≈ 39 person‑years of continuous work
Even with 10 engineers working full time, this is nearly 2 years just to explore the space, before detailed design begins.
For larger real projects with more alternatives per stage and more stages, the "Giza pyramid" of combinations only grows.
Why Manual Exploration Fails
This is not about "good intentions". In practice, teams respond with shortcuts:
- → Heuristics:
"We always use SAG + Ball—it's proven."
→ Instantly discards two‑thirds of grinding alternatives. - → Early pruning:
"Redundancy is too expensive."
→ Removes highly resilient options without proper cost–benefit. - → Precedent bias:
"Our last plant used X, Y, Z—let's copy that."
→ Path dependency, not optimization. - → Limited testing:
Evaluate 50–100 "likely" configurations and pick the best-looking one.
→ No evidence this is even close to the true optimum; often 5–15% below what's achievable.
The phrase "we've always done it this way" is great opportunity to ask in response "awesome...now prove the value!", and if not possible, well...now you can go for your best knife...and .... peel an apple and eat it!...and, be calmed, and then explore seriously the alternative early dismissed.
Why These Decisions Are Hard: The Interdependency Problem
The difficulty is not any single choice, but that every choice depends on all the others:
- • SAG + Ball + mechanical flotation may be robust and forgiving.
- • SAG + Ball + column flotation may create froth instability.
- • HPGR + column flotation can be excellent for fine, uniform feed.
- • HPGR + desalinated water may clash due to power demand.
- • Water recycling strategies interact with reagent schemes and tailings behavior.
Choosing optimally requires understanding these network effects across 5 stages and multiple redundancy schemes. Human working memory can seriously track 2 or 3 interactions at once (..not in Mondays though..); here we face 15 interacting decisions. That is why configuration design is a natural candidate for algorithmic support.
Part 4: Understanding the "Provable Optimum" thing!
4.1 Good Solution vs. Provable Optimum
A good solution:
- • Meets throughput, availability, and budget constraints.
- • Is better than some alternatives seen so far.
- • Feels right to experienced engineers.
A good solution might be 90–95% as valuable as the best possible configuration.
A provable optimum:
- • Meets all constraints.
- • Has higher objective value than any other feasible configuration.
- • Has been verified via exhaustive mathematical search or proof.
- • Cannot be improved without relaxing one or more constraints.
The gap between "good" and "provable optimum" is typically 5–15% of achievable value. For even a mid‑scale expansion, that can mean $50M–$500M. For very large projects, the same percentages imply $250M–$1B.
And we go after the provable optimum because, well.. "This feels right" is not a recognized unit of measurement in financial reporting.
4.2 How Formal Optimization Achieves Proof
The method is conceptually simple:
→ Define decision variables
- • For each stage, which technology alternative?
- • For each stage, which redundancy scheme?
→ Define constraints
- • One alternative per stage.
- • Total CAPEX ≤ budget.
- • System availability ≥ 90%.
- • Flow balance between stages (no unsupplied bottlenecks).
- • Incompatibility rules (certain combinations forbidden).
→ Define objective
Maximize: (production capacity × availability) – (penalties for complexity).
→ Search the space intelligently
- • Test promising configurations.
- • Analyze why infeasible ones fail.
- • Use that information to cut away entire families of bad configurations without testing each.
→ Declare optimality
Once all remaining unexplored configurations are proven to be ≤ the current best, that configuration is the provable optimum.
4.3 Proof as a Mathematical Tournament
Think of the search as a tournament for design configurations:
Round 1 100 promising configurations enter.
Round 2 Poor performers are eliminated; any design with their weaknesses can also be ruled out.
Round 3 50 remain; deeper checks eliminate those with latent bottlenecks.
Round 4 Down to 20 strong candidates; subtle trade‑offs in redundancy and flow balance are tested.
Final Round 1 configuration stands that no unexplored rival can beat.
Unlike sports, this tournament ends with a mathematical certificate: given the model and data, no other feasible configuration can perform better. Engineers can inspect which "players" were eliminated and why. That is, which combinations of choices are intrinsically inferior.
4.4 Proof vs. Real‑World Uncertainty
But hey...this is not magic, BE REALISTIC.. A single formal proof does not magically eliminate uncertainty associated to ambiguities or plain unknowns, but allows you surf comfortably among it. It assumes:
- • Ore characteristics stay within modeled ranges.
- • Equipment availability matches historical or vendor data.
- • Price forecasts and discount rates fall in certain bands.
What formal optimization does provide:
- • A guarantee that under those assumptions, no better configuration exists.
- • Full transparency about assumptions, open to challenge.
- • Sensitivity analysis: how the optimum shifts if ore gets 10% harder, availability is 3% lower, or prices move.
In other words, the configuration is not "guaranteed to be perfect for all futures," but it is guaranteed to be the best response to the scenario being planned for.
But..there are good news!
The Formal Optimization problem can be nested in a "Randomness Explorer" (another mathematical marvel) and then we may explore the full randomness of the problem while breaking all the combinatorial complexity in a joined effort!... BEAUTIFUL!
Part 5: The Mathematical Approach in Business Terms
The Architecture: Two-Part Decision Engine
The optimization adventure has two personalities:
Part 1: The Configuration Strategist
Explores the discrete design space:
- "Should stage 1 use option A or B?"
- "If stage 2 takes HPGR, which flotation options become attractive or risky?"
- "If redundancy is added to grinding, is there still budget for water?"
Part 2: The Feasibility Validator
Rigorously checks each candidate:
- "Does this grinding + flotation combo deliver 90% availability?"
- "Does this water system keep all stages fed without new bottlenecks?"
- "Are any technology compatibility rules violated?"
If a candidate fails, the Validator explains why and sends a "do not try this again" note back to the Strategist so the search doesn't waste time revisiting similar failures.
Part 3: The Randomness Explorer
Let's pull every string in the direction of our unknowns and let's see what happens with value and performance.
So...this is a formal / documented process
The only real "black box" in this workflow should be the undocumented spreadsheet someone left behind, not the optimization logic.
Mathematical Formulation in Plain Language
Executives do not need to see equations to understand the logic of this approach (that's my job...). Core ideas executives must understand are:
Technical or Business Choices...:
- • 5 stages × multiple technologies = 13 technology options.
- • 5 stages × 3 redundancy schemes.
Rules of the Game, this time..:
- → One technology per stage.
- → Total capital ≤ $850M.
- → Bottleneck ≤ 150,000 tpd.
- → System availability ≥ 90%.
- → Upstream must feed downstream.
- → Some pairs are forbidden (e.g., certain grinding and water combinations).
Goal:
Maximize annual production value minus penalties for excessive complexity.
Behind the scenes, this becomes a mixed‑integer optimization model with ~70 binary variables and ~150 constraints in the toy problem. For larger industrial problems, those numbers grow, but they remain tractable.
Part 6: Quantifying the Value of Provable Optimum
6.1 Benchmark Comparison on the Toy Case
Consider an expansion from 85,000 tpd to 150,000 tpd with a target budget of $850M.
Scenario A: Manual Engineering (Traditional)
Follows precedent: SAG+Ball, conventional flotation, no redundancy.
Evaluates 40–50 variants over 6–8 weeks.
Picks a configuration that looks inexpensive and workable.
Results:
- • CAPEX: $798M
- • Expected annual production: 48.2M tonnes
- • Expected availability: 87% (below 90% target, but "close enough")
- • Annual OPEX: $120M
- • 10‑year NPV @ 8%: $17.2B
In year 2, actual availability is only 84%; grinding is a bottleneck due to underestimated ore hardness variability. A retrofit is needed:
- • Retrofit CAPEX: $35M
- • Revised 10‑year NPV: $16.8B ($400M value loss)
Scenario B: Formal Optimization
Models all 26,244 configurations.
Prunes 95% as provably inferior.
Identifies the best configuration in a few minutes.
Results:
- • CAPEX: $837M
- • Expected annual production: 53.2M tonnes (+10%)
- • Expected availability: 93% (meets and exceeds target)
- • Annual OPEX: $118M
- • 10‑year NPV @ 8%: $17.9B
Difference vs. Scenario A
- • Additional production: 1.0M tonnes/year × 10 × $50/t ≈ $500M extra revenue.
- • Avoided retrofit: $35M saved.
- • Higher availability: 6% uptime → 22 extra full‑production days per year.
Total value creation: ≈ $535M over 10 years.
On a mid‑scale $850M project, $535M is more than half the capital outlay. On larger projects, the same relative uplift would be even more dramatic.
6.2 Where the $535M Comes From
→ Capacity Utilization (Higher Production)
HPGR + column flotation, though initially seen as "risky," offers 5.2% higher recovery than SAG+Ball + mechanical cells.
Over 10 years, this yields 50,000 additional tonnes of concentrate, worth $500M.
→ Availability and Uptime
Hot‑standby redundancy at grinding costs $120M CAPEX but increases grinding availability from 92% to 98%.
System availability rises from 87% to 93%; each 1% adds $50M over 10 years.
Net benefit from availability: $300M; after capital, ≈$260M net value.
→ Risk Reduction / Avoided Retrofits
Robust design reduces the likelihood of mid‑project corrections.
A single large retrofit commonly costs $20M–$100M.
Avoiding a $35M retrofit is immediate, tangible savings.
→ OPEX Optimization
Better combinations (e.g., energy‑efficient grinding, water‑lean flotation) trim ≈$2M/year from operating cost.
Over 10 years: ≈ $20M.
Not all of these benefits add linearly (some overlap), but together they solidly support the $535M net improvement.
6.3 Are these reference gains Real?...like...Real Real??
These improvements are grounded in:
- • Published performance data for grinding and flotation technologies.
- • Real vendor and benchmark CAPEX figures.
- • Industry experiences (2–6 year) where it is common for Us to see optimization lifted industrial project NPV by 20–40% on $1.5B–$2B projects. And ..yes...mining is special, but not THAT special... there's plenty of opportunity to apply these proven techniques in mining also.
- • Conservative assumptions: in many actual projects, improvements exceed the toy example.
At the scale of large copper developments, independent studies find that most major projects would have benefited significantly from more rigorous configuration and capacity planning.
6.4 Risk‑Adjusted Returns
Beyond deterministic NPV, formal optimization changes risk exposure:
| Risk Category | Manual Design | With Optimization |
|---|---|---|
| Availability shortfall | 35% chance of 85% availability | 8% chance |
| CAPEX overrun | 40% chance of $900M final cost | 12% chance |
| Retrofit requirement | 25% probability | 5% probability |
| Production miss | 30% chance of 48M tonnes/year | 8% chance |
| Expected value loss from risks | $200M | $30M |
Even holding base‑case NPV constant, the risk‑adjusted value improvement is $170M.
Part 7: Making the Decision
Why Decision-Makers Should Demand Formal Optimization
When committing $850M, and especially when projects climb into the multi‑billion‑dollar range, decision‑makers should insist on three things...(did I say five?):
→ Competing explanations must be tested
If two designs both look reasonable, intuition and precedent are not enough (..like in we are not writing a novel for the people to "like"..are we?). Formal optimization compares them rigorously, and many others never considered.
→ Accountability requires proof
When future stakeholders ask "Why this configuration?", being able to answer "Because, under our assumptions, it is mathematically the best possible" is materially different from "It looked good at the time."
→ Margins are thin at the top
The difference between $16.8B and $17.9B NPV is $1.1B—about 6.5%. Calling 6.5% "good enough" on a project of this scale is not responsible stewardship.
→ Assumptions can be challenged and re‑optimized
All key assumptions (ore hardness, availability, prices) are explicit. If they change, the model can be re‑run in minutes.
→ Decomposition reveals what really matters
The optimizer can show which decisions drive most of the value (e.g., grinding technology and redundancy) and which are secondary (e.g., minor water supply variations).
The Business Case for Formal Optimization
For the toy problem, the article assumes:
- • Optimization effort cost: $200K–$500K
- • Duration: 1–3 months
- • Value creation: $500M–$1B
- • ROI roughly 1,000:1 to 10,000:1
For large real projects, a full‑scope optimization and RAM + Formal Optimization study typically costs in the $450K–$1.5M range and spans 3–6 months, integrating more complex data and broader scope. Even if the uplift "only" reaches 5–10% of NPV, the ROI remains between 150:1 and 2,000:1.
Even highly risk‑averse boards rarely find investments with that profile.
Part 8: Addressing Common Skepticism
"Our engineers have designed plants for 30 years—we know what works."
Experience is invaluable. What it does not provide is:
- • Exhaustive comparison of all feasible alternatives.
- • Proof that what has worked before is best for this orebody, this site, this decade.
Formal optimization starts with engineers' knowledge (constraints, rules, data) and then systematically tests whether there is something better. Thirty years of experience is excellent; thirty years of repeating an untested configuration is less defensible.
"Optimization models are black boxes—how do we trust the result?"
In a well‑designed setup:
- • Every cut, constraint, and exclusion rule can be inspected.
- • Engineers can see exactly why certain configurations were rejected (e.g., insufficient availability, budget breach).
The real black box to be wary of is the spreadsheet that nobody fully understands, not the transparent optimization model...and please don't ask if this is "A.I."..No it is not, and also we don't have the associated problems of lack of explainability.
"The model will be outdated before we finish building."
Conditions will change. That is why:
- • The optimization process is iterative; when assumptions change, the model can be updated and re‑solved quickly...(and quickly here means hours..not weeks)
- • Sensitivity analysis shows how robust the chosen configuration is to these shifts
And, the alternative "locking in a design based on a few manually tested cases" ages far worse.
"Optimization will find an exotic, impractical solution."
Only if the model permits it. If:
Available technologies, compatibility rules, manufacturability constraints, and site limitations are correctly encoded,
Then the optimum will be the best combination of practical, proven technologies, not a fantasy design.
The output is only as "weird" as the inputs allow it to be.
Part 9: Implementation Pathway
A realistic pathway from concept to decision. All times assume you KNOW your business, have data or are concerned enough to get it!
Phase 1: Data Assembly (2–3 weeks)
- • Collect performance data (pilot tests, similar plants, vendors).
- • Assemble CAPEX and OPEX data.
- • Capture operational rules and site constraints.
- • Define objectives and key scenarios.
Phase 2: Model Development (3–4 weeks)
- • Formulate decision variables, constraints, and objective.
- • Build the integrated optimization model with engineers and planners.
- • Test against existing or reference designs to validate behavior.
Phase 3: Optimization Runs (≈1 week)
- • Run the optimizer for base and key sensitivity scenarios.
- • Collect top‑ranked configurations.
- • Analyze patterns in which decisions matter most.
Phase 4: Validation & Engineering Review (2–3 weeks)
- • Engineering teams review the best 3–5 configurations.
- • Stress‑test assumptions and failure modes.
- • Confirm practicality and refine implementation considerations.
Phase 5: Implementation Decision (1–2 weeks)
- • Present options and supporting analysis to leadership.
- • Select preferred configuration.
- • Transition to detailed design.
Total: 2–3 months for the toy problem; 3–6 months for larger, more complex projects.
In both cases, this is short relative to the overall project lifecycle and the value at stake.
Part 10: Conclusion
Designing a mineral processing plant is a high‑stakes, high‑complexity optimization problem:
- • The decision space is huge: tens of thousands of configurations even in simplified examples.
- • Decisions are deeply interdependent: local fixes often create system‑level issues.
- • Uncertainty is inherent: ore, equipment, markets, and regulations all move.
- • Manual, heuristic approaches cannot systematically explore the space or prove optimality.
Traditional approaches typically deliver configurations that are "good enough"—often within 5–15% of what's theoretically achievable. At the scale of today's copper developments, that translates into $500M–$1B in foregone value.
Formal optimization methods directly address this gap:
- • Exhaustive but intelligent search prunes away inferior designs.
- • Rigorous validation enforces constraints and compatibility rules.
- • Mathematical proof certifies that the chosen configuration is the best possible under the given assumptions.
- • Transparent reasoning allows engineers and executives to understand and trust the result.
The result is a provable optimum—not just a defensible design, but a configuration that cannot be improved without changing the rules of the game. In financial terms:
- • Higher production and availability.
- • Fewer retrofits and overruns.
- • Lower risk and greater accountability.
- • NPV improvements in the hundreds of millions to billions of dollars on large projects.
When billions are on the line, "it felt right at the time" is no longer an acceptable justification.
"Because we tested all realistic configurations, and this one is mathematically proven to be the best" is.
And, formal optimization provides the latter, at a tiny fraction of the value it protects.